DrinkPak

Building a Complex Facility for Large-Scale Beverage Manufacturer

Location

Santa Clarita, CA

Size

41-acre campus with 3 standalone buildings, each approx. 140,000 SF.

Project Status

Line 1 completed in 2021

Construction Value

$5,401,906 (Line 1 construction-only value; $15M in equipment purchased directly by owner)

Scope of Work

General Contractor

Project Partners

DrinkPAK, Flow Dynamics, Krones, Catherine McKenna Architects, Saphirre Engineering

About

DrinkPAK is the premier West Coast contract manufacturer of premium alcoholic and non-alcoholic beverages. As the most technologically advanced canned beverage facility in North America, DrinkPAK’s 24/7 operation can produce 2.1 billion cans annually. DrinkPAK engaged DD+B as the General Contractor to construct Line 1 of its new facility. This complex project required close collaboration between DD+B and DrinkPAK to create a functional, innovative facility that provides necessary space for the fast-growing company. From the start of slab demolition to the first produced can of sellable product, DD+B worked tirelessly around the clock to deliver an operational facility in just four months.

Key Project Details

Delivered Speed to Market – DrinkPAK had contracts with some of the beverage industry’s largest producers that reflected immoveable “must produce product by” dates, necessitating a rapid construction timeline
Overcame Obstacles – Permitting delays pushed back the start date, but DD+B was able to achieve the near-impossible, keeping the project on track for the initial delivery date and providing a fully operational facility in four months
Developed Ongoing Partnerships – As a result of the quality and speed of work, DD+B is now working with DrinkPAK on Lines 2 & 3 within the facility