TRIVES ADMIN BUILDING SEISMIC UPGRADE

Trives Admin Building & Seismic Retrofit

Nathanial Trives AdministrationBuilding Gets an Upgrade

Location

1714 21ST  Street, Santa Monica CA

Size

8,068 SF SF

Project Status

Completed April 30th, 2021 – 1.5 month construction schedule

Construction Value

$176,000

Scope of Work

General Contractor

Project Partners

Miyamoto International

About

DD+B partnered with Miaymoto International to seismically upgrade the 2ndfloor and roof framing of the occupied Nathanial Trives Administrationbuilding at Crossroads School for Arts & Sciences in Santa Monica, California. We worked around the existing office furniture to minimize damage to the interior finishes whileadding steel-threaded rod connections to the existing perimeter walls,as well as a roof diaphragm system.

Key Project Details

Completed project while building was occupied

The project was 100% self-performed by DD+B expert craftsmen

Added steel threaded rod connections to existing perimeter walls and the roof diaphragm system